A quick look at the 6.6.11 code indicates that at least in that stream
on windows there is no granularity to the renice - you are either IDLE
(Low) or the default.

Try setting this to 0 instead (this is special cased in the code) but
you will likely get the same priority as the parent process (at least
a step up to Normal)

Matt

On 7/4/06, Ian Chesal <ICHESAL@xxxxxxxxxx> wrote:
I have JOB_RENICE_INCREMENT set to 1 for all my dedicated Windows
machines. I was expecting to see the processes launched by the
condor_starter processes to be High or at least Normal priority when
viewed under taskman. But they're all Low priority . Is that a bug? Is
there a way to get Condor to boost these processes to Normal (or even
better: High)? These are dedicated machines so they're always running
jobs and not cycle stealing.

- Ian

--
Ian R. Chesal <ichesal@xxxxxxxxxx>
Senior Software Engineer

Altera Corporation
Toronto Technology Center
Tel: (416) 926-8300


_______________________________________________
Condor-users mailing list
To unsubscribe, send a message to condor-users-request@xxxxxxxxxxx with a
subject: Unsubscribe
You can also unsubscribe by visiting
https://lists.cs.wisc.edu/mailman/listinfo/condor-users

The archives can be found at either
https://lists.cs.wisc.edu/archive/condor-users/
http://www.opencondor.org/spaces/viewmailarchive.action?key=CONDOR