Re: [Condor-users] Condor 6.8.n: job running delays: RUN TIMES stay at Zero



> Hi Dan, (and Matt from Gloucester Research)
>
> thanks for the feedback. I had formed the impression that we'd need to
> keep the master and slaves in sync as regards major versions but maybe
> not.

Most (all?) non-development releases of Condor are interoperable. For certain the _adjacent releases_ are interoperable. So 6.8.x is interoperable with 7.0.x (there wasn't a 6.10.x IIRC). The Condor team does test for interoperability and where there are features that make them incompatible they're noted in the release notes.

I have been running mixed 6.8.x and 7.0.x farms here, using Windows and Linux execute nodes, quite happily. I run strictly vanilla jobs.

We are in the process of migrating to homogenous 7.4.x setups. Should be done in January. I did test 7.4.x central machines with 6.8.x executors because there was a possibility I'd have to run that way for a period of time. It didn't end up working out that way, but the tests showed no changes in how my vanilla jobs were run. Things were just a-okay.

- Ian

Confidentiality Notice.
This message may contain information that is confidential or otherwise protected from disclosure. If you are not the intended recipient, you are hereby notified that any use, disclosure, dissemination, distribution,  or copying  of this message, or any attachments, is strictly prohibited.  If you have received this message in error, please advise the sender by reply e-mail, and delete the message and any attachments.  Thank you.